Welcome to the broadband4eastrington homepage.

Only days hours minutes and seconds

until Eastrington is broadband enabled!

NEWS FLASH!!!

BT have had a change of heart and moved you date to 15th December THIS YEAR!!!  So in future don't believe BT!

RFS Update

I have contacted BT and asked them why our date is so far away. This is their reply:

"It requires a new CJ cable and the associated transmission system for the ADSL equipment. CJ cables are the core cables which connect together Telephone Exchanges, and also Major Customer Sites, within a zone."

"The anticipated delivery of the cable is November 30 2004, therefore the Backhaul completion date for Eastrington is scheduled at 27 January 2005. ADSL equipment installation and commissioning will be completed for January 27 2004, this to achieve a Ready for Service Date of February 23 2004."

It looks as though the date isn't budging, so I suppose we'll have to wait until 23rd February 2004.

Please note the dates that BT gave us are in 2004, so if you want a realistic date you would have better luck in sticking a pin on a random day in your diary.

We've Got A Date.

Eastrington now has a date for when broadband is going to be installed at our exchange. Unfortunately it's 23rd February 2005. There is very little I can do about the date being so far away, but if there is something that can be done I'll try my hardest to do it. I am trying to find out why our date is so far away and when I do I will update the site. The long date is usually due to building works or cables needing to be laid.










Thanks For Visiting The Site And Helping In The Campaign

Stephen Brough